What changed for small suppliers under the Procurement Act 2023?

The UK's main procurement rules changed in February 2025. These are the changes most likely to affect a small business that bids for public contracts.

Short answer: the Procurement Act 2023 came into force on 24 February 2025. For small suppliers, the main changes are: one registration on Find a Tender that you share with buyers, notices published in one place, no pre-qualification stage for most below-threshold contracts, 30-day payment terms that pass down supply chains, and a duty on buyers to consider barriers facing SMEs. Procurements started under the old rules continue under those rules.

When did the Act start?

The UK government's Transforming Public Procurement page states that the Act came into force on 24 February 2025 and that existing legislation continues to apply to procurements started under the old rules. You may therefore still see both kinds of procedure for a while.

1. One registration on the central digital platform

The central digital platform is an enhanced version of Find a Tender. According to the GOV.UK platform guidance, suppliers register, receive a unique identifier and store core information such as company details, SME status, financial information, connected persons and any exclusion grounds. Only buyers you choose to share it with can see it.

Buyers must confirm that suppliers have registered and shared this information. For notifiable below-threshold contracts, the winning supplier must be registered and provide its unique identifier. Register before you need to bid.

2. Notices in one place

The same guidance says contracting authorities publish procurement notices in one place, on the central digital platform. For below-threshold contracts, this replaces the old requirement to publish on Contracts Finder. You may still see Contracts Finder used for procurements started under the old rules. Our UK contracts guide shows how to set up free Find a Tender alerts.

3. Simpler access to smaller contracts

For regulated below-threshold contracts, GOV.UK guidance says authorities generally cannot restrict tenders by assessing suppliers' suitability first. That removes the separate pre-qualification stage, although suitability can still be assessed when the contract is awarded. Notices are required from £12,000 for central government and £30,000 for other contracting authorities, including VAT. See our below-threshold guide for the exceptions.

4. 30-day payment terms down the supply chain

The payments guidance explains that public contracts are treated as requiring payment of a valid, undisputed invoice within 30 days of receipt. A longer period cannot override this. The terms also cover public sub-contracts and regulated below-threshold contracts, so a subcontractor should also be paid within 30 days. Contracting authorities must publish information on their payment compliance every six months. Some contracts are excluded, such as concessions and contracts awarded by private utilities or schools.

5. A duty to consider barriers facing SMEs

Section 12(4) of the Act requires contracting authorities in a covered procurement to have regard to the particular barriers SMEs may face and to consider whether they can be removed or reduced. A similar duty applies before inviting tenders for regulated below-threshold contracts. The duty does not guarantee that a contract will suit a small supplier, so read lots, values and requirements carefully.

6. Fewer, more flexible procedures

For contracts above the thresholds, the competitive tendering guidance describes two procedures. The open procedure is a single stage in which any interested supplier can submit a tender. The competitive flexible procedure lets the buyer design its own process, which can include several stages and a shortlist. The tender notice and documents explain how each competitive flexible procedure will run, so read them before you start writing.

7. Exclusions and the debarment list

Buyers must consider exclusion grounds and check the debarment list, which is published on GOV.UK. Only a Minister of the Crown can decide to add a supplier, according to the debarment guidance. Keep your core information accurate and up to date: it includes your answers on exclusion grounds.

What should a small supplier do now?

  1. Register your organisation on Find a Tender and complete your core supplier information.
  2. Set up saved searches and alerts on Find a Tender, including lower-value work.
  3. Check payment terms in any contract or subcontract you sign.
  4. For competitive flexible procedures, read the stages and deadlines before deciding to bid. Our bid or no-bid checklist can help.

Quick answers

When did the Procurement Act 2023 come into force?

On 24 February 2025. Procurements started under the old rules continue under those rules.

Do suppliers need to register on Find a Tender?

Yes, before taking part in procurements under the Act. Suppliers register on the central digital platform, receive a unique identifier and share core supplier information with the buyers they choose.

How quickly must public bodies pay suppliers under the Act?

Public contracts are treated as requiring payment of a valid, undisputed invoice within 30 days, and the same 30-day term passes down to public sub-contracts.

Official references