Short answer: for an EU open procedure above the thresholds, the minimum is 35 days from when the contract notice was sent, often 30 days when electronic tenders are accepted. Under the UK Procurement Act 2023 it is usually at least 25 days when tenders are electronic and all documents are available from the start. These are minimums and can be shorter in specific cases, so always use the deadline in the notice.
EU minimum time limits
These apply to procurements covered by Directive 2014/24/EU (Articles 27 to 29). Smaller contracts follow national rules.
| Procedure and stage | Standard minimum | Can be shortened |
|---|---|---|
| Open procedure: tenders | 35 days from the contract notice | By 5 days if electronic tenders are accepted; to 15 days after a qualifying prior information notice or in duly justified urgency |
| Restricted procedure: requests to participate | 30 days | To 15 days in duly justified urgency |
| Restricted procedure: tenders | 30 days from the invitation to tender | By 5 days if electronic; to 10 days after a prior information notice or in urgency; sub-central buyers may agree the period with candidates |
| Competitive procedure with negotiation: requests and initial tenders | 30 days each | Same reductions as the restricted procedure |
UK minimum time limits
Section 54 of the Procurement Act 2023 sets minimum periods for covered procurements:
- Participation period (requests to take part): 25 days, or 10 days where urgency makes 25 impractical.
- Tendering period: 25 days for electronic tenders when all tender documents are provided at the start; 30 days if electronic but documents are not all provided at the start, or if tenders are not electronic; 35 days if neither applies.
- Shorter periods: 10 days after a qualifying planned procurement notice, in urgency, or for some dynamic market and utilities awards. Light-touch contracts have no minimum.
The Act requires the same time limits for every supplier and lists factors buyers must take into account when setting them. The GOV.UK time periods guidance says the aim is to give suppliers reasonable time to prepare.
What this means in practice
- Check the deadline and time zone in the notice. The minimums tell you what the buyer must allow, not what it will allow.
- Note the clarification deadline. It is usually earlier than the submission deadline.
- Register early. A portal account, Find a Tender registration or an ESPD can take time to prepare.
- Watch for planned procurement notices. They can shorten the tender period, so treat them as an early warning.
- Work backwards from the deadline. Allow time for pricing, review and uploading. Our bid or no-bid checklist covers timing.
Hearing about a tender early leaves you more of the response time. Get Contract Alerts checks supported sources each night and emails new matches, showing the deadline where the notice states one.
Quick answers
How long do I have to respond to an EU open tender?
Under Directive 2014/24/EU the minimum is 35 days from the date the contract notice was sent. It can be shortened by five days when electronic tenders are accepted, and to 15 days after a qualifying prior information notice or in duly justified urgency.
What are the minimum tender periods under the UK Procurement Act 2023?
Usually 25 days when tenders are submitted electronically and all tender documents are available from the start. It is 30 or 35 days in other cases and can be 10 days in some cases, such as urgency.
Are these deadlines the time I will actually get?
They are minimums. Buyers can set longer periods, and the deadline in the notice and tender documents is the one that applies.